Construction Progress


Keyton is one of Australia's largest owners, operators and developers of senior living communities. The build of the Clubhouse and Wellness Hub is complete and was officially opened in October 2022. 



December 2023

Sherwin Rise construction update December 2023 image


As 2023 draws to a close, it's been a pleasure watching the vibrant transformation of Stage 2 homes. As we celebrate the successful completion of this phase, we're excited to share that progress is well underway for Stages 3 and 4.

We're delighted to announce the completion of Stage 2, with most residents now comfortably settled into their new home. Our dedicated team is actively addressing any defects and completing miscellaneous works and our goal is to have this wrapped up by the end of the year.

Excitingly, two stunning display homes are now open for viewing. We invite you to explore these spaces and envision the exceptional lifestyle that awaits you in this vibrant community.

Progress is well underway for Stages 3 and 4, with significant advancements in civil works. The site has been benched and is now ready for sewer and water installations. The development team is very close to awarding the contract to the successful tenderer for the next phase of homes, and we anticipate the prospective contractor to start on-site early next year. 




August 2023

Sherwin Rise construction update August 2023 image


The construction team has been working hard over the last month, completing 9 homes and welcoming 4 new residents to the village. A new display home is now open for inspections. 

Progress continues for the remaining 17 units are progressing well, with 5 more to be finished by the end of the month. 

Most of the roofing is completed and the brickwork installation is due to be finished in a few weeks. This paves the way for the removal of scaffolding, enabling the start of external driveway and landscaping work.

Internal plastering, fit off and finishes are also underway with the remaining homes. The builder will progressively complete and hand over these homes in the coming months. 

This is a really exciting time at Sherwin Rise as new residents move in and settle into their new homes within our thriving community!




June 2023

Sherwin Rise construction update June 2023 image


As you may have noticed, there has a been a flurry of activity with over 50 people onsite working hard to build a good quality product for our purchasers.  

Construction is progressing smoothly with Stage 2 well underway, and we anticipate the roofing and brickwork to be completed on all home within the next few weeks. Internals to the homes such as services rough in, plastering, waterproofing and tiling have commenced with the internals taking shape nicely in preparation for joinery and final floor finishes in the coming weeks.

The civil contractor is preparing to initiate pre-construction works in the next few months ahead of the next stage of construction. 



September 2022

Sherwin Rise construction update September 2022 image


The Sherwin Rise Clubhouse and Wellness Hub has definitely morphed into a beauty over the last few months, going from a muddy construction site to now having landscaping finished, pool filled, joinery completed! 

Our construction team has put in a lot of hard work and many hours to get the clubhouse close to completion. All our services, joinery, flooring and finishes are finalised now. 

The team is now working on the final details and touch ups prior to the furniture fit off works occurring in the next few weeks. 

With our opening fast approaching, the site teams have done a spectacular job and we are looking forward to the handover of the clubhouse in the coming weeks.





July 2022

Sherwin Rise construction update July 2022 image


We have had many changes to the Sherwin Rise Clubhouse and Wellness Hub construction over the last few months.

The services fit off stage has officially commenced in the Clubhouse along with installation of joinery, floor finishes, glazing to windows and wall tile install, bringing us that much closer to completion. 

The Wellness Hub is progressing superbly, with ceilings and walls finished, pool tiling commenced, and services being fitted off as well. 

On the external front, we are happy to announce that the landscaping works have started along with the bowling green surface installation in progress, BBQ area sheeting complete, and rendering nearing completion. 

We have also commenced the civil construction works for the roads leading to the clubhouse and stage 2 of our villas. 

Our site teams are kicking big goals this month with progress!





May 2022

Sherwin Rise construction update May 2022 image


The Sherwin Rise Clubhouse and Wellness Hub has definitely morphed into a beauty over the last few months, going from a muddy construction site to now having landscaping finished, pool filled, joinery completed! 

Our construction team has put in a lot of hard work and many hours to get the clubhouse close to completion. All our services, joinery, flooring and finishes are finalised now. 

The team is now working on the final details and touch ups prior to the furniture fit off works occurring in the next few weeks. 

With our opening fast approaching, the site teams have done a spectacular job and we are looking forward to the handover of the clubhouse in the coming weeks.




Sherwin Rise Clubhouse Construction Timelapse Video

September 2021 - April 2022

video thumbnail
Play


April 2022

Sherwin Rise construction update image April 2022


The Sherwin Rise Clubhouse is progressing well with successful construction milestones achieved in the last month. 

The wall framing and trusses is now complete with the roof installation expected to be completed in the next week on the main clubhouse roof then rolling onto the Wellness Centre roof.

Brickwork is nearing 50% complete along with window installation being installed closely behind with the aim to have the main Clubhouse at lock up prior to the Easter break.

Rough-in services will commence in the next week internally in preparation for plastering works to commence in late May.

The Bowling green subgrade has been prepared and ready for the specialist contractor to commence preparation to construct the bowling green surface.